CACERCanadian Energy Regulator Act, s. 96Primary legislationIn force

Regulations

Section 96 of the Canadian Energy Regulator Act authorizes the Regulator to establish regulations governing the design, construction, operation, and abandonment of interprovincial and international pipelines and designated power lines. Regulations must address surveillance, monitoring, safety, security, and environmental protection, and require operators to maintain management systems that incorporate human and organizational factors.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Regulations

96 The Regulator may, with the approval of the Governor in Council, make regulations (a) respecting the design, construction and operation of pipelines, international power lines and interprovincial power lines designated by an order made under section 261; (b) respecting the abandonment of pipelines; (c) respecting surveillance or monitoring measures that, in relation to the activities referred to in paragraphs (a) and (b), are for the safety and security of persons and for the protection of property and the environment; (d) respecting abandoned facilities; (e) requiring holders to have management systems in place and to comply with them; and (f) providing for the elements to be included in those management systems — including human or organizational factors — and respecting any criteria to be met by those management systems.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-96.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-2.11.1GuidanceIn force

Waste Management, Volume I: Management of Radioactive Waste

REGDOC-2.11.1 establishes requirements and guidance for Canadian Nuclear Safety Commission licensees managing radioactive waste, including characterization, storage, and disposal facilities. The document applies to all CNSC licensees under the Nuclear Safety and Control Act and is complemented by CSA N292 standards for comprehensive radioactive waste management oversight.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 73Primary legislationIn force

Alternative dispute resolution

The Canadian Energy Regulator must provide alternative dispute resolution processes for disputes under the Act when all parties consent. Results are non-binding but may be considered by the Commission or designated officers in their decisions and may be made public with party consent.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

il y a 4 heures
CACNSCREGDOC-1.5.1GuidanceIn force

Application Guide: Certification of Radiation Devices or Class II Prescribed Equipment, Version 1.1

REGDOC-1.5.1 v1.1 is a Canadian Nuclear Safety Commission application guide helping applicants prepare and submit certification applications for radiation devices and Class II prescribed equipment. The guide ensures prescribed equipment is safe, protects public health and environment, meets national security standards, and complies with Canada's international nuclear obligations under the Nuclear Safety and Control Act.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

il y a 4 heures