CACERCanadian Energy Regulator Act, s. 269Primary legislationIn force

Power lines not works

International and interprovincial power lines subject to Canadian Energy Regulator orders are excluded from the definition of 'work' under the Canadian Navigable Waters Act, removing them from that Act's regulatory jurisdiction.

Last changed 20 minutes ago.

Extracted view for reading · Original for compliance evidence

Power lines not works

269 Despite the definition work in section 2 of the Canadian Navigable Waters Act, an international power line, or an interprovincial power line in respect of which an order made under section 261 is in force, is not a work to which that Act applies.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-269.html

Canonical document at the regulator. Always cite this URL — not the Vantage detail page — in compliance evidence.

Related in Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

20 minutes ago
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

20 minutes ago
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

20 minutes ago
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

20 minutes ago
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.

20 minutes ago