Country / jurisdiction: South Africa · Year: 2011 · Status: In force · Level: National · Type: Voluntary
In March 2011 Renewable Energy Independent Power Producer Programme (REIPPP) , a public procurement programme, replaced the Feed-in Tariff system, which was introduced in 2009.
Qualifying technologies: onshore wind, solar PV, solar thermal, biomass solid, biogas, landfill gas and small hydro plants.
A ceiling tariff level is established for each technology in the auctions. Winning bidders sign PPAs, which are guaranteed for a period of 20 years.
From 2011 to the beginning of 2015 five rounds of reverse auctions were held for construction and supply of 3,625MW of large-scale (>5MW) renewable energy capacity.
Results of the auction rounds
Auction number
Auction date
Capacity allocated
Round 1
7 December 2011
1.4 GW
Round 2
21 May 2012
1 GW
Round 3
29 October 2013
1.4 GW
Round 4
11 April 2015
200 MW allocated to solar thermal
Round 5
25 June 2015
Results not announced yet