CACERCanadian Energy Regulator Act, s. 359Primary legislationIn force

Delay of issuance

The Canadian Energy Regulator may recommend to the Minister that an electricity export application be designated by Governor in Council order and may delay permit issuance during this process. The Commission must avoid duplicating provincial measures, consider effects on other provinces, verify the applicant offered domestic buyers fair access to available electricity at comparable terms, and account for regulatory factors.

آخر تعديل قبل 4 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Delay of issuance

359 (1) The Commission may make a recommendation to the Minister, which it must make public, that an application for exportation of electricity be designated by order of the Governor in Council under section 360 and may delay issuing a permit during any period that is necessary for the purpose of making such an order. (2) In determining whether to make a recommendation, the Commission must seek to avoid the duplication of measures taken in respect of the exportation by the applicant and the government of the province from which the electricity is to be exported and must take into account (a) the effect of the exportation of the electricity on provinces other than that from which the electricity is to be exported; (b) whether the applicant has (i) informed those who have declared an interest in buying electricity for consumption in Canada of the quantities and classes of service available for sale, and (ii) given an opportunity to buy electricity on conditions as favourable as the conditions specified in the application to those who, within a reasonable time after being so informed, demonstrate an intention to buy electricity for consumption in Canada; and (c) any factors that are specified in the regulations.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-359.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

قبل 4 ساعات
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

قبل 4 ساعات