CACERCanadian Energy Regulator Act, s. 329Primary legislationIn force

Form of compensation payment if land taken

Under Canadian Energy Regulator Act section 329, when a company takes or leases land, the Regulator must direct compensation payment at the landowner's option as either a lump sum or periodic payments. Interest may be awarded at the prime business loan rate from the date of land entry or when damages first occurred.

آخر تعديل قبل 6 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Form of compensation payment if land taken

329 (1) If the Commission makes an award of compensation in favour of a person whose lands are taken by a company, the Commission must, by order, direct, at the option of that person, that the compensation or any part of it be made by one lump sum payment or by periodic payments of equal or different amounts over a specified period of time. (2) If the Commission makes an award of compensation in favour of any person other than a person referred to in subsection (1), the Commission may, by order, direct, at the request of that person, that the compensation or any part of it be made by periodic payments of equal or different amounts over a specified period of time and that there be a periodic review of the compensation or part of the compensation. (3) Every award of compensation made by the Commission in respect of lands acquired or leased by a company must include provision for those matters referred to in paragraphs 321(2)(b) to (h) that would be required to be included in a land acquisition or lease agreement referred to in section 321. (4) The Commission may, by order, direct a company to pay interest on the amount of any compensation awarded by the Commission at the lowest rate of interest quoted by banks to the most credit-worthy borrowers for prime business loans, as determined and published by the Bank of Canada for the month in which, as the case may be, (a) the company entered the lands in respect of which the compensation is awarded; or (b) the damages suffered as a result of the operations of the company first occurred. (5) Interest may be awarded under subsection (4) from the date the event referred to in paragraph (4)(a) or (b), as the case may be, occurred or from any later date that the Commission may specify in its award.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-329.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

قبل 6 ساعات
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

قبل 6 ساعات
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

قبل 6 ساعات
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

قبل 6 ساعات
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

قبل 6 ساعات