CACERCanadian Energy Regulator Act, s. 214Primary legislationIn force

Orders

The Canadian Energy Regulator Commission may exempt pipelines up to 40 km long, previously constructed pipelines, and associated infrastructure (tanks, compressors, storage facilities) from specified regulatory provisions. Exemption applications must be decided within 300 days of complete submission; the Lead Commissioner may exclude certain periods with public disclosure, and the Minister may grant extensions. The Commission may impose conditions on exemptions.

آخر تعديل قبل 51 دقيقة.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Orders

214 (1) The Commission may, by order, exempt from the application of any or all of the provisions of section 179, subsection 180(1) and sections 182, 198, 199 and 213 (a) pipelines or branches of or extensions to pipelines, of not more than 40 kilometres in length; (b) pipelines that have already been constructed; and (c) any tanks, reservoirs, storage or loading facilities, pumps, racks, compressors, interstation communication systems, real or personal property, or immovable or movable, and any connected works. (2) In any order made under subsection (1), the Commission may impose any conditions that it considers appropriate. (3) If an application for an order under subsection (1) is made, the Commission must, within the time limit specified by the Lead Commissioner, either make an order under that subsection or dismiss the application. (4) The time limit specified by the Lead Commissioner must be no longer than 300 days after the day on which the applicant has, in the Commission’s opinion, provided a complete application. (5) In the circumstances prescribed by regulations made under section 216, the Lead Commissioner may specify that a period is to be excluded from the calculation of the time limit. The Lead Commissioner must provide reasons for doing so. (6) The Minister may, by order, grant one or more extensions of the time limit specified under subsection (3). (7) The Commission must make public the time limit specified under subsection (3), any period that is excluded under subsection (5), the reasons for the exclusion and any extension of time granted under subsection (6). (8) Despite subsections (3) to (6), if the Lead Commissioner considers that an application for an exemption is related to an application for a certificate in respect of a pipeline, the time limit within which to make an order under subsection (1) or to dismiss the application for an exemption expires on the day on which the certificate is issued or the application for the certificate is dismissed. (9) A failure by the Commission to make an order under subsection (1) or dismiss the application within the required time limit does not affect its jurisdiction to deal with the application or its obligation to make the order or to dismiss the application, and anything done by it in relation to the application remains valid.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-214.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACERCanadian Energy Regulator Act, s. 64Primary legislationIn force

Enforcement of orders

Canadian Energy Regulator decisions and orders may be registered with Federal or provincial superior courts and enforced as court orders by filing a certified copy with the court registrar. If a registered decision is subsequently rescinded or varied, the court order is vacated and the modified decision may be re-registered following standard court procedures.

قبل 51 دقيقة
CACERCanadian Energy Regulator Act, s. 349Primary legislationIn force

Transfer of licences

The Canadian Energy Regulator may transfer licences under this Division on application. Non-minor or non-technical transfers require ministerial approval based on public interest assessment. The Commission may impose new or modified conditions on transferred licences as necessary to fulfil the Act's purposes.

قبل 51 دقيقة
CACERCanadian Energy Regulator Act, s. 351Primary legislationIn force

Suspension or revocation of licences — contravention

The Canadian Energy Regulator may suspend or revoke a licence if the holder breaches a licence condition or if the regulator deems it in the public interest (with ministerial approval). The licence holder must receive notice of the alleged contravention and an opportunity to respond before any order is made.

قبل 51 دقيقة
CACERCanadian Energy Regulator Act, s. 92Primary legislationIn force

Statutory Instruments Act

Section 92 of the Canadian Energy Regulator Act exempts orders and directions issued by the Commission, designated officers, or inspection officers from statutory instrument classification when they apply to a single person or entity, a single regulated facility, or are issued immediately for safety, security, environmental protection, or property protection purposes.

قبل 51 دقيقة
CACERCanadian Energy Regulator Act, s. 96Primary legislationIn force

Regulations

Section 96 of the Canadian Energy Regulator Act authorizes the Regulator to establish regulations governing the design, construction, operation, and abandonment of interprovincial and international pipelines and designated power lines. Regulations must address surveillance, monitoring, safety, security, and environmental protection, and require operators to maintain management systems that incorporate human and organizational factors.

قبل 51 دقيقة