CACERCanadian Energy Regulator Act, s. 213Primary legislationIn force

Leave required

Pipeline companies must obtain a leave order from the Canadian Energy Regulator Commission before opening a pipeline or section for transmission of hydrocarbons or other commodities. Leave is granted only when the Commission is satisfied the pipeline can safely operate.

آخر تعديل قبل 5 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Leave required

213 (1) A pipeline or section of a pipeline must not be opened for the transmission of hydrocarbons or any other commodity by a company unless an order granting it leave to do so has been made by the Commission. (2) Leave may be granted by the Commission under this section only if it is satisfied that the pipeline may safely be opened for transmission.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-213.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

قبل 5 ساعات
CACNSCREGDOC-1.5.1GuidanceIn force

Application Guide: Certification of Radiation Devices or Class II Prescribed Equipment, Version 1.1

REGDOC-1.5.1 v1.1 is a Canadian Nuclear Safety Commission application guide helping applicants prepare and submit certification applications for radiation devices and Class II prescribed equipment. The guide ensures prescribed equipment is safe, protects public health and environment, meets national security standards, and complies with Canada's international nuclear obligations under the Nuclear Safety and Control Act.

قبل 5 ساعات
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

قبل 5 ساعات
CACNSCREGDOC-1.1.1GuidanceIn force

Site Evaluation and Site Preparation for New Reactor Facilities, Version 1.3

REGDOC-1.1.1 establishes Canadian Nuclear Safety Commission requirements for site evaluation and preparation of new reactor facilities, including nuclear power plants and small modular reactors. Applicants must characterize sites, assess severe external events and multiple simultaneous accidents, and demonstrate adequate safety measures during site preparation and construction using a risk-informed, graded approach.

قبل 5 ساعات
CACERCanadian Energy Regulator Act, s. 160Primary legislationIn force

Application

Section 160 of the Canadian Energy Regulator Act establishes a compensation claims tribunal where persons, organizations, governments, and Indigenous governing bodies may file claims for damages caused by pipeline releases from designated companies within prescribed timeframes. The Tribunal Chairperson must promptly assign claims to panels and notify all relevant parties.