CACERCanadian Energy Regulator Act, s. 200Primary legislationIn force

Additional material to be deposited

Pipeline companies must deposit additional materials with the Canadian Energy Regulator beyond standard filings, including plans, specifications, and drawings for pipeline components, as required by the regulator.

آخر تعديل قبل 4 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Additional material to be deposited

200 In addition to the plans, profiles and books of reference, a company must, as soon as feasible, deposit with the Regulator any additional material, including plans, specifications and drawings with respect to any part of its pipeline, as the Commission may require.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-200.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACERCanadian Energy Regulator Act, s. 73Primary legislationIn force

Alternative dispute resolution

The Canadian Energy Regulator must provide alternative dispute resolution processes for disputes under the Act when all parties consent. Results are non-binding but may be considered by the Commission or designated officers in their decisions and may be made public with party consent.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 160Primary legislationIn force

Application

Section 160 of the Canadian Energy Regulator Act establishes a compensation claims tribunal where persons, organizations, governments, and Indigenous governing bodies may file claims for damages caused by pipeline releases from designated companies within prescribed timeframes. The Tribunal Chairperson must promptly assign claims to panels and notify all relevant parties.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 186Primary legislationIn force

Decision by Governor in Council

Section 186 of the Canadian Energy Regulator Act grants the Governor in Council authority to issue binding orders on pipeline certificate applications following CER recommendations. The Governor may approve certificates with conditions, dismiss applications, or refer recommendations for reconsideration. Orders must include written reasons demonstrating consideration of relevant factors and be issued within 90 days (extendable). Orders are final, must be published in the Canada Gazette within 15 days, and the CER must comply within seven days.

قبل 4 ساعات