CACERCanadian Energy Regulator Act, s. 185Primary legislationIn force

Impact Assessment Act

Section 185 of the Canadian Energy Regulator Act transfers certificate application authority for designated projects under the Impact Assessment Act from the Commission to an independent review panel. The panel exercises powers under sections 182-184, coordinates with energy and environment ministers, and must submit reports within Impact Assessment Act timelines.

آخر تعديل قبل 4 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Impact Assessment Act

185 If the application for a certificate relates to a designated project, as defined in section 2 of the Impact Assessment Act, that is subject to an impact assessment under that Act, (a) the Commission’s powers, duties and functions under section 182, subsections 183(1) and (2) and section 184 are to be exercised and performed by a review panel established under subsection 47(1) of that Act; (b) in subsections 183(1) and 184(5), a reference to the Minister is to be read as a reference to the Minister and the Minister of the Environment; (c) the report referred to in subsection 183(1) is to be submitted within the time limit established under section 37.1 of that Act; (d) subsections 183(3) to (10) do not apply; and (e) subsection 189(1) applies with respect to the review panel.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-185.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACERCanadian Energy Regulator Act, s. 73Primary legislationIn force

Alternative dispute resolution

The Canadian Energy Regulator must provide alternative dispute resolution processes for disputes under the Act when all parties consent. Results are non-binding but may be considered by the Commission or designated officers in their decisions and may be made public with party consent.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

قبل 4 ساعات
CACNSCREGDOC-1.5.1GuidanceIn force

Application Guide: Certification of Radiation Devices or Class II Prescribed Equipment, Version 1.1

REGDOC-1.5.1 v1.1 is a Canadian Nuclear Safety Commission application guide helping applicants prepare and submit certification applications for radiation devices and Class II prescribed equipment. The guide ensures prescribed equipment is safe, protects public health and environment, meets national security standards, and complies with Canada's international nuclear obligations under the Nuclear Safety and Control Act.

قبل 4 ساعات
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

قبل 4 ساعات
CACNSCREGDOC-2.11.1GuidanceIn force

Waste Management, Volume I: Management of Radioactive Waste

REGDOC-2.11.1 establishes requirements and guidance for Canadian Nuclear Safety Commission licensees managing radioactive waste, including characterization, storage, and disposal facilities. The document applies to all CNSC licensees under the Nuclear Safety and Control Act and is complemented by CSA N292 standards for comprehensive radioactive waste management oversight.

قبل 4 ساعات