Country / jurisdiction: Lithuania · Year: 2023 · Status: In force · Level: National · Type: Voluntary
These proposals consider the National Energy Independence Strategy and the National Energy and Climate plan to install a wind farm in the Baltic Sea. The wind farm would reach 700 MW and produce 2.5-3 TWh of electricity per year, which is 25% of Lithuania's electricity demand. It may take up to 8 years to install and the territory planned in the Baltic Sea covers an area of 137.5 square km, with an average wind speed of 9 m/s.
Official source: http://enmin.lrv.lt/en/news/ministry-of-energy-prepares-proposals-on-the-location-and-capacity-of-wind-power-turbines-in-the-baltic-sea
Source
https://www.iea.org/policies/11497Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.