Replacement of panel member during hearing

Section 48 of the Canadian Energy Regulator Act establishes procedures for replacing panel commissioners during hearings. If a commissioner becomes unavailable or resigns during a hearing, the Lead Commissioner may appoint a replacement to continue the hearing and participate in the decision. If unavailability occurs after the hearing concludes but before the decision is finalized, remaining commissioners may proceed unanimously to make the decision without replacement.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Replacement of panel member during hearing

48 (1) If a panel is conducting a hearing and a commissioner on the panel is unable to act or resigns during the hearing, the Lead Commissioner may authorize another commissioner to replace that commissioner for the rest of the hearing and to participate in the decision or, as applicable, finalize the report required under subsection 183(1). (2) If a panel is conducting a hearing and a commissioner on the panel is unable to act or resigns after the conclusion of the hearing but before the decision is made or, as applicable, the report required under subsection 183(1) is finalized, the remaining commissioners may — if unanimous — make the decision or finalize the report as if the commissioner were present and participating.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-48.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

il y a 4 heures
CACNSCREGDOC-1.5.1GuidanceIn force

Application Guide: Certification of Radiation Devices or Class II Prescribed Equipment, Version 1.1

REGDOC-1.5.1 v1.1 is a Canadian Nuclear Safety Commission application guide helping applicants prepare and submit certification applications for radiation devices and Class II prescribed equipment. The guide ensures prescribed equipment is safe, protects public health and environment, meets national security standards, and complies with Canada's international nuclear obligations under the Nuclear Safety and Control Act.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

il y a 4 heures
CACNSCREGDOC-1.1.1GuidanceIn force

Site Evaluation and Site Preparation for New Reactor Facilities, Version 1.3

REGDOC-1.1.1 establishes Canadian Nuclear Safety Commission requirements for site evaluation and preparation of new reactor facilities, including nuclear power plants and small modular reactors. Applicants must characterize sites, assess severe external events and multiple simultaneous accidents, and demonstrate adequate safety measures during site preparation and construction using a risk-informed, graded approach.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 73Primary legislationIn force

Alternative dispute resolution

The Canadian Energy Regulator must provide alternative dispute resolution processes for disputes under the Act when all parties consent. Results are non-binding but may be considered by the Commission or designated officers in their decisions and may be made public with party consent.

il y a 4 heures