CACERCanadian Energy Regulator Act, s. 365Primary legislationIn force

Variation or transfer of permits or licences

The Canadian Energy Regulator Commission may vary or transfer permits and licences for electricity exportation either upon application or its own initiative. When doing so, the Commission may impose new or modified conditions it deems necessary to fulfil the Act's purposes and provisions.

Dernière modification il y a 1 heure.

Vue extraite pour la lecture · Original pour les preuves de conformité

Variation or transfer of permits or licences

365 (1) The Commission may, on application or its own initiative, vary a permit or licence issued in respect of the exportation of electricity and may, on application, transfer such a permit or licence. (2) In varying or transferring a permit or licence, the Commission may impose — in addition to or in lieu of any conditions to which the permit or licence was previously subject — any conditions that the Commission considers necessary or appropriate in order to give effect to the purposes and provisions of this Act.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-365.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 1 heure
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.