CACERCanadian Energy Regulator Act, s. 330Primary legislationIn force

Costs

Section 330 of the Canadian Energy Regulator Act establishes cost allocation rules for compensation disputes. If the awarded compensation exceeds 85% of the company's settlement offer, the company must pay all legal, appraisal, and reasonable costs incurred by the claimant. If the award is at or below 85% of the offer, the Commission has discretion to allocate costs.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Costs

330 (1) If the amount of compensation awarded to a person by the Commission exceeds 85% of the amount of compensation offered by the company, the company must pay all legal, appraisal and other costs determined by the Commission to have been reasonably incurred by that person in asserting that person’s claim for compensation. (2) If the amount of compensation awarded to a person by the Commission does not exceed 85% of the amount of compensation offered by the company, the legal, appraisal and other costs incurred by that person in asserting their claim for compensation are at the discretion of the Commission, and the Commission may, by order, direct the company or any other party to the proceedings to pay the whole or any part of those costs.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-330.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 4 heures
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 4 heures