Determinations regarding compensation

Under Canadian Energy Regulator Act section 327, the Commission determines compensation disputes between energy companies and landowners when parties cannot agree. The Commission considers market value of acquired lands, changes in value over time, loss of use, adverse effects on remaining lands, nuisance and noise from operations, potential damage from company activities, livestock/property loss, relocation difficulties, and other relevant circumstances.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Determinations regarding compensation

327 (1) If a company and an owner of lands have not agreed on any matter relating to the compensation payable under this Part, the Commission, on application by a company or any owner, must, by order, determine that matter. (2) In determining any matter under subsection (1) for the acquisition or lease of lands, the Commission must consider the following factors: (a) the market value of the lands taken by the company; (b) if periodic payments are being made under an agreement or an order of the Commission, changes in the market value referred to in paragraph (a) since the agreement or order of the Commission or since the last review and adjustment of those payments, as the case may be; (c) the loss of use to the owner of the lands taken by the company or whose use is otherwise restricted by the operation of section 335; (d) the adverse effect of the taking of the lands by the company on the remaining lands of an owner, including by restricting their use by the operation of section 335; (e) the nuisance, inconvenience and noise that may reasonably be expected to be caused by or arise from or in connection with the operations of the company; (f) the damage to lands in the area of the lands taken by the company that might reasonably be expected to be caused by the operations of the company; (g) loss of or damage to livestock or other personal property or movable affected by the operations of the company; (h) any special difficulties in relocation of an owner or their property; (i) any other factors that the Commission considers appropriate in the circumstances; and (j) other prescribed factors that are prescribed under paragraph 333(e). (3) For the purpose of paragraph (2)(a), market value is the amount that would have been paid for the lands if, at the time of their taking, they had been sold in the open market by a willing seller to a willing buyer.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-327.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 4 heures
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.