CACERCanadian Energy Regulator Act, s. 301Primary legislationIn force

Suspension or revocation

The Canadian Energy Regulator may suspend or revoke an authorization by order if the holder requests it, consents to it, or breaches a condition. Before revoking for breach, the regulator must provide written notice and opportunity to be heard.

Dernière modification il y a 1 heure.

Vue extraite pour la lecture · Original pour les preuves de conformité

Suspension or revocation

301 (1) The Commission may, by order, suspend or revoke an authorization if the holder applies for or consents to the suspension or revocation or the holder has contravened a condition of the authorization. (2) The Commission must not make an order under subsection (1) for a contravention unless the Commission provides the holder with notice of the alleged contravention and gives them an opportunity to be heard.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-301.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 1 heure
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.