Temporary prohibition — ground disturbances

The Canadian Energy Regulator prohibits ground disturbances near international or interprovincial power lines for three working days after a location request is made, or until a later agreed date. The Commission may grant exemptions under appropriate conditions.

Dernière modification il y a 1 heure.

Vue extraite pour la lecture · Original pour les preuves de conformité

Temporary prohibition — ground disturbances

276 (1) Orders made under subsection 275(1) and regulations made under subsection 275(2) may provide for the prohibition of ground disturbances in an area that is situated in the vicinity of an international or interprovincial power line and that may extend beyond the prescribed area during the period that starts when a request to locate the line is made to the holder of the permit or certificate issued in respect of the line and ends (a) at the end of the third working day after the day on which the request is made; or (b) at any later time that is agreed to between the holder and the person making the request. (2) The Commission may, by order made on any conditions that the Commission considers appropriate, exempt any person from the application of an order or regulation made under section 275.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-276.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 1 heure
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 1 heure
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.