CACERCanadian Energy Regulator Act, s. 275Primary legislationIn force

Orders

The Canadian Energy Regulator Commission may issue orders governing the design, construction, operation, and abandonment of facilities crossing interprovincial and international power lines. Orders authorize facility crossings, regulate ground disturbances, govern vehicle operation, allocate construction costs, and specify activities. The Regulator may also make complementary regulations with Governor in Council approval.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Orders

275 (1) The Commission may, by order, give directions (a) governing the design, construction, operation and abandonment of facilities constructed across, on, along or under an international or interprovincial power line; (b) prescribing the area for the purposes of subsection 273(1); (c) authorizing the construction of facilities across, on, along or under an international or interprovincial power line; (d) authorizing ground disturbances within the prescribed area; (e) governing the measures to be taken in relation to (i) the construction of facilities across, on, along or under an international or interprovincial power line, (ii) the construction of an international or interprovincial power line across, on, along or under facilities, other than railways, and (iii) ground disturbances within the prescribed area; (f) authorizing the operation of vehicles or mobile equipment across an international or interprovincial power line and governing the measures to be taken in relation to that operation; (g) governing the apportionment of costs directly incurred as a result of a construction or disturbance authorized under this subsection; (h) specifying activities for the purposes of paragraph (a) of the definition ground disturbance in section 2 in respect of international or interprovincial power lines; and (i) authorizing a holder of a permit or certificate to give an authorization referred to in paragraph (c), (d) or (f) on any conditions that the holder considers appropriate. (2) The Regulator may make regulations respecting any matter referred to in paragraphs (1)(a) to (f) and (h). (3) The Regulator may, with the approval of the Governor in Council, make regulations (a) governing the apportionment of costs directly incurred as a result of a construction or disturbance authorized under this section; and (b) authorizing a holder of a certificate or permit issued under this Part to give an authorization referred to in paragraph (1)(c), (d) or (f) on any conditions that the holder considers appropriate.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-275.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 4 heures
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 4 heures