CACERCanadian Energy Regulator Act, s. 211Primary legislationIn force

Approval of deviations

Pipeline companies must submit detailed plans, profiles, and reference documentation to the Canadian Energy Regulator for approval of deviations from previously approved or constructed pipelines. The Regulator may exempt submission requirements if deviations serve public purposes or benefit the pipeline, provided deviations do not exceed Commission-specified distance limits from the original centerline.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Approval of deviations

211 (1) If a deviation is required by a company to be made in a pipeline, or a part of a pipeline, that has been constructed or for which a detailed route has been approved, a plan, profile and book of reference of the part of the pipeline proposed to be changed, showing the deviation proposed to be made, must be submitted to the Regulator for the approval of the Commission. (2) If the plan, profile and book of reference of the part of the pipeline proposed to be changed have been approved by the Commission, and copies have been deposited as provided in this Act with respect to the original plan, profile and book of reference, the company may make the deviation, and all the provisions of this Act are applicable to the part of the pipeline, as changed or proposed to be changed, in the same manner as they are applicable to the original pipeline. (3) The Commission may exempt a company from all or any of the provisions of this section if the deviation was made or is to be made for the purpose of benefiting a pipeline, or for any other public purpose, if it considers it appropriate to do so, but the deviation must not exceed the distance that is specified by the Commission from the centre line of the pipeline located or constructed in accordance with the plans, profiles and books of reference approved by the Commission under this Act.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-211.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACERCanadian Energy Regulator Act, s. 260Primary legislationIn force

Effect of election

Section 260 of the Canadian Energy Regulator Act establishes that filing an election under section 259 for international power lines prevents new permit issuance, converts pending applications to certificate applications, and revokes existing permits or certificates. Applicants or permit holders who file the election and are acquiring or leasing land become liable for all damages and reasonable costs incurred by landowners from abandonment of such acquisition or lease.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 274Primary legislationIn force

Relocation

The Canadian Energy Regulator may order holders of international or interprovincial power line permits or certificates to relocate infrastructure when necessary to facilitate construction or relocation of other facilities. The regulator determines cost allocation between parties, requires mandatory consultation procedures, and may order reimbursement of reasonable costs incurred by persons making submissions.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 160Primary legislationIn force

Application

Section 160 of the Canadian Energy Regulator Act establishes a compensation claims tribunal where persons, organizations, governments, and Indigenous governing bodies may file claims for damages caused by pipeline releases from designated companies within prescribed timeframes. The Tribunal Chairperson must promptly assign claims to panels and notify all relevant parties.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 186Primary legislationIn force

Decision by Governor in Council

Section 186 of the Canadian Energy Regulator Act grants the Governor in Council authority to issue binding orders on pipeline certificate applications following CER recommendations. The Governor may approve certificates with conditions, dismiss applications, or refer recommendations for reconsideration. Orders must include written reasons demonstrating consideration of relevant factors and be issued within 90 days (extendable). Orders are final, must be published in the Canada Gazette within 15 days, and the CER must comply within seven days.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 73Primary legislationIn force

Alternative dispute resolution

The Canadian Energy Regulator must provide alternative dispute resolution processes for disputes under the Act when all parties consent. Results are non-binding but may be considered by the Commission or designated officers in their decisions and may be made public with party consent.

il y a 4 heures