Matters to be taken into account

The Canadian Energy Regulator must consider all written submissions and public hearing representations when approving pipeline construction plans, routes, and methods. The Regulator may approve sections where no submissions have been filed.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Matters to be taken into account

203 (1) Subject to subsections (2) and 202(6), the Commission must not approve a plan, profile and book of reference unless it has taken into account, in order to determine the best possible detailed route of the pipeline and the most appropriate methods and timing of its construction, (a) all written statements filed under subsection 201(3) or (4); and (b) all representations made to the Commission at a public hearing. (2) The Commission may approve a plan, profile and book of reference in respect of any section or part of a pipeline if no written statement under subsection 201(3) or (4) has been filed in respect of that section or part.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-203.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 4 heures
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.