CACERCanadian Energy Regulator Act, s. 201Primary legislationIn force

Notice to owners

Pipeline companies must serve written notice on all affected landowners and publish notices describing the proposed pipeline route and CER head office location. Landowners have 30 days from service to file written opposition; other persons anticipating adverse effects have 30 days from publication to oppose. The Regulator must publish notices on its website.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Notice to owners

201 (1) If a company has submitted to the Regulator a plan, profile and book of reference under subsection 199(1), the company must, in the form and manner specified by the Commission, (a) serve a notice on all owners of lands proposed to be acquired, leased, taken or used, insofar as they can be ascertained; and (b) publish a notice in at least one issue of a publication, if any, in general circulation within the area in which the lands are situated. (2) The notices mentioned in subsection (1) must describe the proposed detailed route of the pipeline, the location of the head office of the Regulator and the right of the owner and of persons referred to in subsection (4) to make, within the period referred to in subsection (3) or (4), as the case may be, representations to the Commission respecting the detailed route of the pipeline. (2.1) The Regulator must publish on its website any notice that is published under paragraph (1)(b). (3) If an owner of lands who has been served with a notice under subsection (1) wishes to oppose the proposed detailed route of a pipeline, the owner may, within 30 days after the day on which the notice is served, file with the Regulator a written statement setting out the nature of their interest and the grounds for their opposition to that route. (4) A person who anticipates that their lands may be adversely affected by the proposed detailed route of a pipeline, other than an owner of lands referred to in subsection (3), may oppose the proposed detailed route by filing with the Regulator, within 30 days after the day on which the last notice referred to in subsection (1) is published, a written statement setting out the nature of their interest and the grounds for their opposition to that route.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-201.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 308Primary legislationIn force

Limitations

Authorization holders for Canadian offshore renewable energy projects and offshore power lines must obtain prior written approval from the Canadian Energy Regulator before selling, transferring, purchasing, acquiring, or leasing such projects or their facilities, equipment, and systems, or before amalgamating with another company.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.