CACERCanadian Energy Regulator Act, s. 198Primary legislationIn force

Approval

Pipeline companies must obtain a Canadian Energy Regulator certificate before constructing any pipeline section, comply with all certificate conditions, secure Regulator approval of construction plans and specifications, and deposit certified copies in relevant land registries.

Dernière modification il y a 2 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Approval

198 Except as otherwise provided in this Act, a company must not begin the construction of a section or part of a pipeline unless (a) the Commission has issued a certificate in respect of the pipeline; (b) the company has complied with all applicable conditions to which the certificate is subject; (c) the plan, profile and book of reference of the section or part of the pipeline have been approved by the Commission; and (d) copies, certified by the Regulator, of the approved plan, profile and book of reference have been deposited in the land registry office or other office where title to land is recorded for the area through which the section or part of the pipeline is to pass.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-198.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-1.2.3GuidanceIn force

Licence Application Guide: Licence to prepare Site for a Deep Geological Repository

REGDOC-1.2.3 is the Canadian Nuclear Safety Commission's licence application guide for entities seeking to obtain a licence to prepare sites for deep geological repositories (DGR) of radioactive waste. It establishes comprehensive requirements across management systems, radiation protection, safety analysis, environmental protection, waste management, security, and public engagement, applying a risk-proportionate graded approach throughout the DGR lifecycle and site preparation stages.

il y a 2 heures
CACERCanadian Energy Regulator Act, s. 64Primary legislationIn force

Enforcement of orders

Canadian Energy Regulator decisions and orders may be registered with Federal or provincial superior courts and enforced as court orders by filing a certified copy with the court registrar. If a registered decision is subsequently rescinded or varied, the court order is vacated and the modified decision may be re-registered following standard court procedures.

il y a 2 heures
CACERCanadian Energy Regulator Act, s. 349Primary legislationIn force

Transfer of licences

The Canadian Energy Regulator may transfer licences under this Division on application. Non-minor or non-technical transfers require ministerial approval based on public interest assessment. The Commission may impose new or modified conditions on transferred licences as necessary to fulfil the Act's purposes.

il y a 2 heures
CACERCanadian Energy Regulator Act, s. 351Primary legislationIn force

Suspension or revocation of licences — contravention

The Canadian Energy Regulator may suspend or revoke a licence if the holder breaches a licence condition or if the regulator deems it in the public interest (with ministerial approval). The licence holder must receive notice of the alleged contravention and an opportunity to respond before any order is made.

il y a 2 heures
CACERCanadian Energy Regulator Act, s. 92Primary legislationIn force

Statutory Instruments Act

Section 92 of the Canadian Energy Regulator Act exempts orders and directions issued by the Commission, designated officers, or inspection officers from statutory instrument classification when they apply to a single person or entity, a single regulated facility, or are issued immediately for safety, security, environmental protection, or property protection purposes.