CACERCanadian Energy Regulator Act, s. 184Primary legislationIn force

Order to reconsider

Section 184 of the Canadian Energy Regulator Act enables the Governor in Council to order the Commission to reconsider its report recommendations or conditions. Orders are binding and must be published in the Canada Gazette within 15 days. The Commission must submit a reconsideration report confirming, modifying, or replacing recommendations and conditions while addressing all necessary public interest factors. The reconsideration report is final unless another order is issued.

Dernière modification il y a 4 heures.

Vue extraite pour la lecture · Original pour les preuves de conformité

Order to reconsider

184 (1) After the Commission has submitted its report under section 183, the Governor in Council may, by order, refer the recommendation, or any of the conditions, set out in the report back to the Commission for reconsideration. (2) The order may direct the Commission to conduct the reconsideration taking into account any factor specified in the order and it may specify a time limit within which the Commission must complete its reconsideration. (3) The order is binding on the Commission. (4) The order must be published in the Canada Gazette within 15 days after the day on which it is made. (5) The Commission must, within the time limit specified in the order, if one was specified, (a) reconsider its recommendation or any condition referred back to it, as the case may be; (b) prepare and submit to the Minister a report on its reconsideration; and (c) make the report public. (6) In the reconsideration report, the Commission must (a) if its recommendation was referred back, either confirm the recommendation or set out a different recommendation; and (b) if a condition was referred back, confirm the condition, state that it no longer supports it or replace it with another one. (7) Regardless of what the Commission sets out in the reconsideration report, the Commission must set out in the report all the conditions, that it considers necessary or in the public interest, to which the certificate would be subject if the Governor in Council were to direct that the certificate be issued. (8) Subject to subsection (9) and section 186, the Commission’s reconsideration report is final and conclusive. (9) After the Commission has submitted its report under subsection (5), the Governor in Council may, by order, refer the Commission’s recommendation, or any of the conditions, set out in the report back to the Commission for reconsideration. If it does so, subsections (2) to (8) apply.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-184.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 4 heures
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 307Primary legislationIn force

Application of sections 317 and 318

Section 307 of the Canadian Energy Regulator Act extends regulatory sections 317 and 318 to offshore renewable energy projects and offshore power lines by substituting references to companies with persons and pipelines with offshore facilities, ensuring equivalent regulatory requirements.

il y a 4 heures
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 4 heures