CACERCanadian Energy Regulator Act, s. 117Primary legislationIn force

Commission of violation

Under Canadian Energy Regulator Act section 117, any person who contravenes or fails to comply with designated provisions, orders, decisions, or conditions commits a violation subject to penalties determined by regulation. Penalties are designed to promote compliance rather than punish.

Dernière modification il y a 37 minutes.

Vue extraite pour la lecture · Original pour les preuves de conformité

Commission of violation

117 (1) Every person who contravenes or fails to comply with a provision, order, decision or condition designated under paragraph 115(1)(a) commits a violation and is liable to a penalty of an amount to be determined in accordance with the regulations. (2) The purpose of the penalty is to promote compliance with this Act and not to punish.

Source

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-117.html

Document officiel chez le régulateur. Citez toujours cette URL — et non la page de détail Vantage — dans les preuves de conformité.

Connexes dans Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

il y a 37 minutes
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

il y a 37 minutes
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

il y a 37 minutes
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

il y a 37 minutes
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.

il y a 37 minutes