INTIEABrazil · Brazil Renewable Energy AuctionsPolicyIn force

Brazil Renewable Energy Auctions

In 2004 Brazil reformed its electricity sector (adoption of Laws 10.847 and 10.848) and started utilising energy auction system to procure electricity. The procurement system was based on load forecast. Existing and new generators are allowed to participate in the auction.…

Last changed 11 years ago.

Extracted view for reading · Original for compliance evidence

Lifecycle

  1. Effective
  2. Last change

Country / jurisdiction: Brazil · Year: 2007 · Status: In force · Level: National · Type: Voluntary

In 2004 Brazil reformed its electricity sector (adoption of Laws 10.847 and 10.848) and started utilising energy auction system to procure electricity. The procurement system was based on load forecast. Existing and new generators are allowed to participate in the auction. Short, medium and long term electricity procurement contracts are awarded through auction process.

In 2007 system was amended in order to allow technology specific auctions specially design for renewable generators. The first technology specific auction was held in 2008 procuring electricity from biomass . The first wind auction took place in 2009.

There are two types of auctions: new energy auctions and reserve energy auctions .

New energy auctions (alternative energy auctions) contract new capacity needed to meet growing electricity demand. Contracted generators have to start delivering electricity within three (marked A-3) or five years (A-5) from the auction. Usually held once a year. Contracts are awarded for period of 20 to 30 years, depending on the technology. Hydropower plants receive contract for 30 years. Wind and biomass projects receive PPAs for period of 20 years.

Reserve energy auctions are used to contract additional capacity on order to increase capacity reserve. This type of auction is technology specific.

Renewable electricity auctions held in Brazil

No.

Auction title and type

Date held

Technology

Awarded capacity (MW)

1 st alternative energy auction

June 2007

Biomass

97

Small hydro

541

1 st capacity auction

August 2008

Biomass

1284

2 nd capacity auction

Dec 2009

Wind

1806

3 rd capacity auction

26 Aug 2010

Small hydro

30

Biomass

648

Wind

528

2 nd alternative auction

27 Aug 2010

Small hydro

101

Biomass

65

Wind

1520

12 th energy auction

Aug 2011

Wind

1068

Biomass

198

4 th capacity auction

Aug 2011

Wind

921

Biomass

297

13 th energy auction

Dec 2011

Wind

977

Biomass

100

Large hydro

135

14 th energy auction

Dec 2012

Cancelled

10

15 th energy auction

Dec 2012

Wind

289

Large hydro

294

11

5 th capacity auction

Aug 2013

Wind

1500

12

16 th energy auction

Aug 2013

Large hydro

400

Small hydro

218

Biomass

647

13

17 th energy auction

Nov 2013

Wind

867.6

14

18 th energy auction

Dec 2013

Wind

2338

Small hydro

308

Biomass

162

Large hydro

700

15

19 th energy auction

June 2014

16

6 th capacity auction

Oct 2014

Solar PV

890

Wind

769

17

20 th energy auction

Nov 2014

Wind

926

Biomass

611

Small hydro

43

18

3 rd alternative energy

April 2015

Wind

90

Biomass

389

19

22 nd energy auction

Aug 2015

Biomass

pending

Wind

Natural Gas

Small hydro

20

7 th capacity auction

Aug 2015

Solar PV

pending

21

8 th capacity auction

Nov 2015

Solar PV

pending

Official source: http://www.planalto.gov.br/ccivil_03/_Ato2007-2010/2007/Decreto/D6048.htm

Source

https://www.iea.org/policies/5750

Canonical document at the regulator. Always cite this URL — not the Vantage detail page — in compliance evidence.

Related in International

INTIEACanada · National Energy Code of Canada for BuildingsPolicyIn force

National Energy Code of Canada for Buildings

The National Energy Code of Canada for Buildings (NECB) 2025 is a national model code that sets technical requirements that address the protection of the environment in the design and construction of new buildings and in subsequent alterations. The 2025 edition was published in…

10 days agoeff.
INTIEACanada · Deep Retrofit Accelerator InitiativePolicyIn force

Deep Retrofit Accelerator Initiative

Launched by Natural Resource Canada in February 2023, the Deep Retrofit Accelerator Initiative (DRAI) provides funding to organisations and projects that facilitate the development of deep retrofits in commercial, institutional, and mid- or high-rise multi-unit residential…

10 days agoeff.
INTIEASweden · Tax exemption for pure and highblend biofuelsPolicyIn force

Tax exemption for pure and highblend biofuels

The Swedish scheme to promote the use of sustainable biofuels in transport has been prolongated until 31 December 2032 with an estimated budget of 1.3 USD billion (SEK 14.2 billion).    The scheme was originally approved by the Commission in November 2003 and prolonged several…

10 days agoeff.
INTIEACanada · Codes Acceleration Fund (CAF)PolicyIn force

Codes Acceleration Fund (CAF)

Launched by Natural Resource Canada in 2023,  the Codes Acceleration Fund (CAF) provides funding to support efforts to accelerate and contribute to code (or regulation) adoption, compliance and enforcement. The programme provides funding to:   • provinces, territories,…

10 days agoeff.
INTIEACanada · Energy Efficiency Regulations, 2016 - Electric motorsPolicyIn force

Energy Efficiency Regulations, 2016 - Electric motors

The Energy Efficiency Regulations set standards for several industrial products and industrial applications of products including motors, air compressors, pumps, dry-type transformers and ceiling fans.     The standards for electric motors were regularly updated, lastly in 2022…

10 days agoeff.