Lifecycle
- Effective
- Last change
Country / jurisdiction: Lithuania · Year: 2021 · Status: In force · Level: National · Type: Voluntary
The Sustainable Electricity measure of the Green Transformation as part of the National Resilience and Recovery Plan is meant to promote production, transmission, and use of electricity consumption using the most cost effective technologies, improving institutional mechanisms, and providing incentives for businesses and citizens to invest. Lithuania will implement 242.39 million EUR from EU funding, 157.44 million from private entities and 55.716 million EUR from its national budget. Planned investments include onshore solar and wind power plants, a solar power park, and storage facilities.
Official source: https://finmin.lrv.lt/uploads/finmin/documents/files/Naujos%20kartos%20Lietuva_2021_05_14.pdf
Source
https://www.iea.org/policies/13673Canonical document at the regulator. Always cite this URL — not the Vantage detail page — in compliance evidence.