Prohibition — construction or ground disturbance

Section 273 of the Canadian Energy Regulator Act prohibits construction, ground disturbance, and vehicle/mobile equipment operation on, across, or under international and interprovincial power lines without CER authorization. Exceptions permit vehicle operation on travelled highways and public roads. The CER Commission may order facility owners to reconstruct, alter, or remove installations that threaten line safety or security.

آخر تعديل قبل ساعتين.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Prohibition — construction or ground disturbance

273 (1) It is prohibited for any person to construct a facility across, on, along or under an international or interprovincial power line or engage in an activity that causes a ground disturbance within the prescribed area unless the construction or activity is authorized by the orders or regulations made under section 275 and done in accordance with them. (2) It is prohibited for any person to operate a vehicle or mobile equipment across an international or interprovincial power line unless (a) that operation is authorized by orders or regulations made under section 275 and done in accordance with them; or (b) the vehicle or mobile equipment is operated within the travelled portion of a highway or public road. (3) The Commission may, by order, direct the owner of a facility constructed across, on, along or under an international or interprovincial power line in contravention of this Act, the Commission’s orders or the regulations to do anything that the Commission considers necessary for the safety or security of the line and, if the Commission considers that the facility may impair the safety or security of the operation of the line, direct the owner to reconstruct, alter or remove the facility.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-273.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

قبل ساعتين
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

قبل ساعتين
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

قبل ساعتين
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

قبل ساعتين
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.