CACERCanadian Energy Regulator Act, s. 258Primary legislationIn force

Where certificate required

Under Canadian Energy Regulator Act section 258, the Governor in Council may designate international power lines by order to require certificate-based regulation instead of permits. Any existing permit must be revoked within 45 days of permit issuance. Once designated, no new permits may be issued and all applications must be processed as certificate applications.

آخر تعديل قبل 3 ساعات.

العرض المستخرج للقراءة · النص الأصلي للأدلة الامتثالية

Where certificate required

258 (1) The Governor in Council may, by order, (a) designate an international power line as an international power line that is to be constructed and operated in accordance with a certificate issued under section 262; and (b) revoke any permit issued in respect of the line. (2) No order may be made under subsection (1) in respect of a power line more than 45 days after the issuance of a permit in respect of the line. (3) If an order is made under subsection (1), (a) no permit is to be issued in respect of the power line; and (b) any application in respect of the line is to be dealt with as an application for a certificate.

المصدر

https://laws-lois.justice.gc.ca/eng/acts/C-15.1/section-258.html

الوثيقة الرسمية لدى الجهة التنظيمية. استشهد دائماً بهذا الرابط — لا بصفحة تفاصيل Vantage — في أدلة الامتثال.

ذات صلة في Canada

CACNSCREGDOC-3.5.1GuidanceIn force

Information Dissemination: Licensing Process for Class I Nuclear Facilities and Uranium Mines and Mills, Version 2.1

قبل 3 ساعات
CACNSCREGDOC-3.5.4GuidanceIn force

Pre-licensing Review of a Vendor’s Reactor Design

قبل 3 ساعات
CACERCanadian Energy Regulator Act, s. 2Primary legislationIn force

Definitions

Section 2 of the Canadian Energy Regulator Act establishes statutory definitions for federal energy infrastructure regulation, including abandoned facilities and pipelines, oil and gas exports and imports, ground disturbance thresholds for pipeline protection, and incorporates Indigenous governing bodies and knowledge in energy decision-making processes.

قبل 3 ساعات
CACERCanadian Energy Regulator Act, s. 140Primary legislationIn force

Reimbursement — measures taken by government institution

The Canadian Energy Regulator Commission may order pipeline operators to reimburse federal, provincial, municipal governments, Indigenous bodies, and other persons for reasonable costs incurred responding to unintended or uncontrolled releases of oil, gas, or other commodities from pipelines, even if costs exceed the operator's statutory liability limits.

قبل 3 ساعات
CACERCanadian Energy Regulator Act, s. 32Primary legislationIn force

Jurisdiction

The Canadian Energy Regulator has exclusive jurisdiction to investigate non-compliance with the Act and authorization conditions, inquire into accidents involving pipelines, abandoned pipelines, international power lines, and offshore renewable energy projects, and issue findings, recommendations, and orders in the public interest.

قبل 3 ساعات